Concrete Placing, Finishing and Texturing

A uniform thickness of concrete (according to the design) should be placed on the prepared subgrade, adequately consolidated, and struck off to the proper elevation. All concrete should be placed continuously to prevent the formation of "cold joints". Wherever placment operations stop, a bulkhead will be installed to form a straight joint. Concrete should not be placed on a frozen subgrade. The sequence of finishing operations should be as follows: strike off and consolidation, floating (if necessary), edging, and texturing.

 

No finishing operations should be performed when there is excess moisture or bleed water on the surface. In general, adding water to the surface of the concrete to assist in finishing operations is not recommended.

 

Check the pavement surface with a ten foot straight edge.

 

A uniformly textured surface should be provided.